|

One of the first things you should do before starting a transportation
project is determine whether or not the project constitutes use
(an adverse impact to, or occupancy of, a Section 4[f] resource). There
are four main types of use:
This portion of the document will introduce you to each type and help
you to recognize use in various projects.
FEE SIMPLE
This type of use involves a Right-of-Way
(ROW) acquisition of Section 4(f) land as part of a transportation project.
In other words, the transportation agency directly purchases the property,
and the property sustains a permanent impacttypically, changing
from Section 4(f) property to a transportation facility.
Back to List
PERMANENT EASEMENT
With this type of use, the transportation agency acquires a permanent
easement on the Section 4(f) property. Examples of permanent easement
use include maintenance access, utility access, placement of stream outfall
structures. Permanent easement use differs from fee simple use in that
the easement may not necessarily change the landscape permanently.
Back to List
TEMPORARY EASEMENT
During the construction phase of the highway project, a temporary easement
such as a staging or access area may be needed. Once the easement is no
longer needed, the Section 4(f) resource must be restored to the condition
in which it was originally found. This may involve re-grading or re-vegetating
the area.
Note: Temporary easement use may be considered Section 4(f) use
if the land is subject to temporary or permanent adverse changes, such
as contour alterations or removal of mature trees and other vegetation.
Temporary easement use may not be considered a Section 4(f) use if all
of the following conditions exist:
- The land use is of short duration (defined as less than the time
needed for the construction phase)
- There is no change in ownership of the land
- The transportation agency has no long term or indefinite vested interest
in the land
- There are no temporary or permanent adverse changes to the resource
- The project involves only a minor portion of the resource
Conditions must be evaluated on a case-by-case basis to determine whether
or not a particular activity constitutes use of a Section 4(f) resource.
Communication with the state Department of Transportation (DOT) and the
official
with jurisdiction is critical in order to get a determination from
the Federal
Highway Administration (FHWA).
Back to List
CONSTRUCTIVE
This form of use involves an indirect impact to the Section 4(f) resource.
Here the project does not physically incorporate the resource but is close
enough to it to severely impact activities associated with it, and to
substantially impair it in the eyes of the FHWA. 
Constructive use may include impacts such as noise, access restrictions,
vibration, ecological intrusions and visual impacts. Note that constructive
use does not occur under the following conditions:
- When there is a finding of "No historic properties affected"
or "No adverse effect" under Section 106
- When noise resulting from the project does not approach or exceed
the FHWA noise abatement criteria or when it is considered barely
perceptible
- When administration approval is made prior to designation of significance
- When a transportation project reserves a portion of Section 4(f)
property for future use
- When the overall combined impacts do not result in substantial impairment
- When impacts are mitigated to a condition equal to or better than
the no-build option
- When a change in accessibility is considered minor
- When vibration impacts are considered minor or mitigated
FHWA policy maintains that a constructive use of Section 4(f) land, though
possible, is rare and should therefore be examined carefully. Project
documents should contain the analysis of proximity effects and a discussion
of whether or not there is substantial impairment to a Section 4(f) resource.
The term "constructive use" need not be used, except when responding to
review comments in environmental documents that specifically address constructive
use. In cases where it has been determined that there is a constructive
use, the draft Section 4(f) evaluation must be cleared with the FHWA Washington
Headquarters prior to circulation.
Back to List
|