|

This project example illustrates various challenges inherent in assessing
and documenting potential impacts to Section 4(f) wildlife and waterfowl
refuges. It presents a number of realistic scenarios that you should
consider, as though you were conducting an actual Section 4(f) evaluation.
With this project example, we will walk you through the general decision-making
process established under Section 4(f) for refuges.
CRITERIA
Keep in mind that in order to qualify as a Section 4(f) resource, a
wildlife or waterfowl refuge must meet the following criteria:
-
It must be publicly owned
-
Its major purpose must be that of a refuge
-
It must be significant as a refuge
As you read through this project example, pay especially close attention
to major purpose, as it plays an important role in the determination
of the selected alternative.
PROJECT PURPOSE & NEED
The state transportation agency was evaluating an existing roadway system through a national
wildlife refuge. The roadway included a bridge that crossed a river
and was damaged in a storm. The existing road provided a poor level
of service, including a substandard westbound line of site immediately
before the bridge, resulting in a high accident rate. The project purpose
was to improve traffic capacity and improve safety conditions.

RESOURCES
The entire project area was located within the boundaries of a national
wildlife refuge, so the refuge was the only Section 4(f) resource, per
se, to be evaluated (the bridge was not historic). However, within the
refuge there were several areas whose value as important refuge elements
had to be assessed and compared.
Based on a review of the refuge master plan and meetings with officials
with jurisdiction at the Department of the Interior (DOI), the state transportation agency discovered
the following:
-
Portions of the refuge included critical forest habitat
areas for a variety of plant and animal species, including a federally
listed endangered plant inhabiting the northern points of the critical
forest habitat areas, just south of the existing highway. The master
plan highlighted the protection of these habitats as one of the most
important goals of the refuge. Some of the more sensitive areas in
the refuge were not open to the public.
-
The refuge had wetlands just
south of the existing roadway on the east side of the stream that
passed under the bridge.
-
The refuge had a recreation area that included camping
facilities and hiking trails, and a maintenance area that included
administrative offices and storage facilities.
| QUESTION:
Based on the state transportation agency's findings during coordination, does it appear
that some portions of the refuge were more valuable than others,
with respect to the refuge's major purpose? |
The state transportation agency concluded that some portions of the refugenamely, the
critical forest habitat and wetlandswere more valuable than others,
in terms of the resource's major purpose. Nevertheless, Section 4(f)
protection still applied to the refuge as a whole.
ALTERNATIVES
The state transportation agency worked with the FHWA, the DOI officials with jurisdiction, and
various environmental resource agencies to develop four project alternatives:
No-Build Alternative This option was limited to maintenance
of the existing alignment, some minor shoulder improvements, and additional
signage. It did not meet the project purpose and need, but it was
carried forward for further study as an avoidance alternative.
Upgrade Alternative This option entailed
the widening of the roadway along the north side of the existing alignment
(avoiding the critical habitat to the south), as well as the straightening
of the roadway geometry at the two curves, and replacement of the bridge.
This alternative met the project purpose and need, and it was carried
forward.
Alternative 1 This option entailed a new roadway alignment
to the south of the existing road. It met the project purpose and
need, and was carried forward for further study.
Alternative 2 This option entailed a new roadway alignment
to the north of the existing road. It met the project purpose and
need, and was carried forward for further study.

USE
With the exception of the No-Build option, all of the alternatives entailed
Section 4(f) use, since they involved impacts to property within the
refuge boundary. Here is a brief assessment of each alternative and
its impacts:
No-Build Alternative This option entailed no impacts
since it did not require use of any Section 4(f) resources in the
project area.
Upgrade Alternative This option required use of one
acre of critical forest habitat, including the
areas designated for the protection of federally listed flora (at
the two curves where the road would be straightened). In addition,
it required use of a strip of land along the northside of the road.
Alternative 1 This option required use of both forest
habitat areas and roughly two acres of wetlands.
Alternative 2 This option required use of two buildings
in the maintenance area and a small portion of the campground. Although
the campground would merely be clipped by Alternative 2,
its utility would be affected by increased noise.
The state transportation agency evaluated all of these impacts to see if the project qualified
for a programmatic Section 4(f) evaluation. The project did not qualify,
because it involved the consideration of new alignments.
AVOIDANCE & MINIMIZATION
Avoidance
The state transportation agency staff re-evaluated the study area to see if there was a
potential avoidance alternative besides the No-Build option. They considered
modifying the upgrade alternative, but realized that any widening of
the existing roadway would require additional right-of-way and therefore
constitute use.
The state transportation agency also considered bypass alternatives
to the north and south of the refuge, but neither of these represented
a serious option. A northern bypass would result in severe impacts to
ten acres of forested land and twenty acres of farmland just north of
the refuge, and a southern bypass alternative would result in 12 business
displacements in a new development immediately south of the refuge.
Both would require radical shifts in roadway geometry.
Minimization
As required, the state transportation agency staff developed a plan to minimize Section 4(f)
impacts along the Upgrade Alternative and Alternatives 1 and 2.
Upgrade Alternative
Minimization efforts for this option entailed adding retaining walls
and narrowing the typical section to minimize impacts to critical forest
habitat.
Alternative 1 In addition, the state transportation agency
focused on shifting the alignment closer to the existing road in order
to take a narrower section of the critical forest habitat and wetlands.
Retaining walls were also considered.
Alternative 2 Minimization efforts for this option required
additional coordination with the official with jurisdiction to determine
which of the refuge's resources along this alignment were more valuable
in light of the refuge's major purpose. The officials indicated that
the campground was of greater value than the maintenance area, so minimization
efforts focused on shifting the alignment to the south at the campground
and narrowing the typical section. Retaining walls were also considered.
MITIGATION
Because the Upgrade Alternative and Alternatives 1 and 2 required
use of the refuge, they also required mitigation. For the Upgrade Alternative
and Alternative 1, the state transportation agency considered reforestation,
habitat restoration and enhancements. For Alternative 2, the agency
considered the construction of new recreational and maintenance facilities,
and on-site building relocation.
Replacement lands, consisting mainly of farmland, were considered to
the north of the refuge for all three minimization alternatives. Final
mitigation measures were determined through coordination with the official
with jurisdiction.
| QUESTION:
Can you think of any other mitigation measures that could be used
within the refuge boundary? Think broadly; be creative! |
It is worth noting that the state transportation agency did not limit
itself to the mitigation measures that were readily apparent to them;
rather, they asked the official with jurisdiction to offer specific
mitigation needs beyond those related to the impacted land.
Although the agreed-upon measures in this case were closely related
to the affected resources, they could have included a variety of options
such as educational opportunities; the construction of trails, wildlife
passages, and interpretive signs; stream stabilization projects; and
the reconfiguration of campgrounds and other infrastructure improvements.
DRAFT EVALUATION
After a thorough evaluation of the resources and coordination with the
agencies, the state transportation agency was able to develop a draft
evaluation that included the following elements:
-
Introduction
-
Description of the Proposed Action
-
Description of the Section 4(f) Resources
-
Description of Impacts
-
Avoidance and Minimization Alternatives
-
Mitigation
-
Coordination
The state transportation agency's goal was to develop a document that would (a) provide enough
data to pass an FHWA legal sufficiency review and (b) reflect the state transportation agency's
effort in coordinating with the officials with jurisdiction, the various
agencies, and other interested parties. Potential minimization and mitigation
efforts were included.
FINAL EVALUATION
Following the comment period, the state transportation agency prepared a final evaluation, which
included all the elements of the draft evaluation, plus the following:
-
A discussion of the basis for concluding that there
is no feasible and prudent avoidance alternative
-
Information demonstrating that the proposed action
includes all possible planning to minimize harm
-
Information demonstrating that the selected alternative
causes the least harm and is also feasible and prudent
-
A summary of the official coordination with the
DOI headquarters
-
Copies of all official coordination and a summary
of other relevant Section 4(f) comments received, with an analysis
and response to any questions raised
-
A concluding statement
SUMMARY
The state transportation agency and FHWA agreed that there was no
feasible and prudent avoidance alternative. The only avoidance alternative
that was seriously considered was the No-Build option, which did not
meet the project purpose and need, so it was not feasible and prudent.
The complete avoidance alternatives to the north and south were never
fully developed because (a) they would present community disruption
of an extraordinary magnitude and interfere substantially with farming
operations, and (b) as bypass options, they did not meet the project
purpose and need.
Consequently, the state transportation agency had to select either the Upgrade Alternative,
Alternative 1, or Alternative 2. All three of these options involved
impacts to the refuge.
Of the three, Alternative 2 was the option that presented the least
harm to the refuge. Although it would impact two buildings in the maintenance
area and a small portion of the campground, the state transportation agency determined that
these elements of the refuge could be satisfactorily replaced through
mitigation, whereas the critical forest habitat and wetlandswhich
would be affected by the Upgrade Alternative and Alternative 1could
not. Furthermore, given the overall purpose of the refuge, the state transportation agency determined
that the critical forest habitat had greater value than the campground
and maintenance facilities. Thus, Alternative 2 was the state transportation agency's selected
alternative.
| |
 |
 |
|
 |
|