Cultural resources

This project example illustrates the various challenges inherent in assessing and documenting potential impacts to cultural resources. It presents a number of realistic scenarios that you should consider, as though you were conducting an actual Section 4(f) evaluation. With this project example, we will walk you through the general decision-making process established under Section 4(f) for cultural resources.

Note on Section 106: Be aware that while Section 4(f) may resemble Section 106 with respect to its application to cultural resources, the two statutes are distinct laws with distinct processes that should be observed separately. The following project example relates to Section 4(f) only. (For more information, see Related Statutes.)

CRITERIA
Keep in mind that in order to qualify as a Section 4(f) resource, a cultural resource must meet the following criteria:

  • It must be of national, state or local significance.
  • If it is not on or eligible for listing on the National Register of Historic Places (NRHP), but credible information indicates that it has local significance, the Federal Highway Administration (FHWA) may apply Section 4(f) to the site is not on or eligible for listing on the National Register of Historic Places (NRHP), but credible informationFederal Highway Administration (FHWA).

Keep in mind that a cultural resource may be publicly or privately owned.

PROJECT PURPOSE & NEED
The state transportation agency has identified two operational concerns regarding an existing roadway running through a small town: high vehicular and pedestrian accident rates, and through-traffic capacity deficiencies. The purpose of their project was to improve the safety problems and through-traffic operations.

RESOURCES
Through public meetings and correspondence with the SHPO, the state transportation agency concluded that the town's central historic district would qualify for Section 4(f) protection because it was eligible for listing on the NRHP. In addition, they identified six resources within the district—two of which were individually eligible (the hotel and the tavern), and the rest of which were contributing elements. Here are the six resources:

  • Hotel
  • Cemetery
  • Store
  • Tavern
  • Bridge
  • Mill Archeological Site

ALTERNATIVES
The state transportation agency worked with the public and town officials, as well as environmental resource agencies, to develop five project alternatives:

No Build Alternative —This option entailed maintenance to the existing bridge and roadway, and included re-striping within the town limits to allow for pedestrian crosswalks. However, it did not address the level of service or capacity issues and therefore did not meet the project purpose and need. Nevertheless, it was carried forward as an avoidance alternative.

Upgrade
Alternative —This option entailed widening of the existing roadway and replacement of the existing bridge on the east side of town. It met the project purpose and need, and was carried forward for further study.

Alternative 1
—This option consisted of a new roadway and bridge to the south of the existing roadway. It met the project purpose and need, and was carried forward for further study.

Alternative 2
— This option consisted of a new roadway and bridge to the north of the existing roadway. It met the project purpose and need, and was carried forward for further study.

Alternative 3 — This option consisted of a new roadway and bridge to the north of the existing roadway, but south of Alternative 2. It met the project purpose and need, and was carried forward for further study.



USE
The state transportation agency staff continued coordination with the SHPO and the Federal Highway Administration (FHWA) in order to assess probable impacts to the Section 4(f) resources within each alignment. Here's what they found:

No Build Alternative — This option did not require the use of any Section 4(f) resources in the project area.

Upgrade Alternative — This option required the use of sidewalk frontage throughout the town, as well as the removal and demolition of the hotel, the store, and the tavern in order to widen the existing road and improve roadway vertical geometry.

Alternative 1 — This option required use of 1.5 acres of the cemetery and two acres of the historic district along the southern border. It also required use of a quarter acre of the mill archeological site, although preservation in place was not warranted for this resource, according to town officials and the SHPO.

Alternative 2 — This option did not require use of Section 4(f) resources. However, it did require the use of one acre of sensitive wetlands, as well as a half acre of threatened and endangered species habitat.

Alternative 3 — This option required the use of property in the northeast corner of the historic district, although it did not require the use of any contributing or individually historic elements within the district boundaries.

AVOIDANCE & MINIMIZATION

Avoidance
The state transportation agency concluded that the only avoidance options were the No-Build Alternative and Alternative 2. They investigated an avoidance option to the south of the historic district, but concluded that it was not an option because it would require direct impacts to an entire community. Here is a brief assessment of the two avoidance alternatives:

No-Build Alternative — As indicated in the Alternatives section, this option clearly avoided Section 4(f) impacts but did not meet the project purpose and need.

Alternative 2 — This option clearly avoided Section 4(f) impacts and met the project purpose and need; however, coordination with environmental resource agencies indicated that there were unique problems associated with it. The Fish and Wildlife Service and state and federal environmental agencies determined that the proposed alignment would impact threatened and endangered species habitat, and wetlands of special state concern. While it would not impact any Section 4(f) resources, it would impact other sensitive resources.

Minimization
Because the Upgrade Alternative, Alternative 1, and Alternative 3 involved impacts to Section 4(f) resources—or, in the case of Alternative 3, what appeared to be possible impacts—minimization efforts for these alternatives were required.

Upgrade Alternative — Minimization efforts initially focused on reducing direct impacts to the hotel, the store and the tavern. However, the state transportation agency determined that such measures were not possible because the three resources are in close proximity to the existing street and to each other. The alignment could not be shifted in either direction without adversely affecting one or more of them. In addition, the typical section could not be narrowed while still fulfilling the project purpose and need.

Alternative 1 — The state transportation agency considered efforts to minimize impacts to the cemetery and the historic district by shifting the alignment slightly to the south, and by using retaining walls and landscape buffers.

Alternative 3 — This option required a portion of the historic district in the northeast corner, possibly constituting Section 4(f) use. However, coordination with the state transportation agency and FHWA raised doubts about whether this option did constitute use, when the SHPO indicated that the impacted property was not individually historic and was not a contributing element of the historic district.

After circulation of the draft Section 4(f) evaluation, and as part of coordination, the state transportation agency committed to visual screening and depression of the roadway to minimize visual impacts to the historic district. The SHPO and FHWA ultimately determined that, with these minimization measures, Alternative 3 would have no adverse effect on the historic district itself and therefore did not constitute Section 4(f) use.

QUESTION: If the SHPO and FHWA determined that Alternative 3 did have an adverse effect on the historic district, would there be Section 4(f) use?

In this case, an adverse effect ruling by the SHPO and FHWA would constitute Section 4(f) use; however, it is important to note that adverse effect is a Section 106 term that does not necessarily equate to Section 4(f) use in all cases.

MITIGATION
The state transportation agency considered potential mitigation measures for the Upgrade Alternative and Alternatives 1 and 3.

Upgrade Alternative — The state transportation agency considered fully documenting the cultural resources that would be affected, including the hotel, tavern, and store. This documentation would be included on a plaque describing the historic significance of the resources. Another option was to provide the documentation as part of an exhibit panel to be housed somewhere within the historic district.

Relocation of these structures was considered, but initial studies indicated that this measure was not possible, due to the age and condition of the structures.

Alternative 1 — For this alternative, mitigation efforts focused on fully documenting the importance of both the cemetery and the archeological mill site. Options included interpretive plaques to be placed near each resource. The cemetery plaque would commemorate the important people buried there.

Alternative 3 — No Section 4(f) mitigation measures were developed for this alternative, since the portion of the district affected was neither a contributing element of the historic district nor individually historic.


DRAFT EVALUATION

Before preparing a draft evaluation, the state transportation agency considered the possibility of using two Section 4(f) programmatic evaluations that have been prepared for use nationwide—one for historic sites, the other for historic bridges. However, when they examined the programmatic agreements, they discovered that neither of the programmatic evaluations was applicable to the project, because the project did not meet all the criteria. Consequently, neither of the two was used.

QUESTION: Why, specifically, were the programmatic evaluations for historic sites and bridges considered not applicable to this project? Which criteria were not met?

(For help with the above question, see Applicability under historic sites and historic bridges.)

With the programmatic options excluded, the state transportation agency developed an individual draft evaluation comprised of the following elements:

  • Introduction
  • Description of the Proposed Action
  • Description of the Section 4(f) Resources
  • Description of Impacts
  • Avoidance and Minimization Alternatives
  • Mitigation
  • Coordination

The state transportation agency's goal was to develop a document that would (a) provide enough data to pass an FHWA legal sufficiency review and (b) reflect the state transportation agency's effort in coordinating with the official with jurisdiction, the various agencies, and other interested parties. Potential minimization and mitigation efforts were included.

FINAL EVALUATION
Through coordination with the FHWA, the state transportation agency determined that the project had a feasible and prudent avoidance alternative—Alternative 3. Their next step was to developed a final evaluation, in which they discussed the basis for making this determination. Here is an overview of what the final evaluation included:

  • A discussion of the basis for concluding that Alternative 3 was a feasible and prudent avoidance alternative
  • Evidence of coordination with the local officials, SHPO and FHWA in making Section 4(f) resource determinations
  • Copies of all official coordination and a summary of other relevant Section 4(f) comments received, with an analysis and response to any questions raised
  • A Memorandum of Agreement (MOA) with the SHPO, detailing any necessary Section 106 compliance and mitigation measures
  • A concluding statement

SUMMARY
The state transportation agency and FHWA determined that this project did have a feasible and prudent avoidance alternative. The No-Build option would have avoided Section 4(f) impacts but was not feasible and prudent because it did not meet the project purpose and need. The other avoidance option, Alternative 2, was not feasible and prudent because it presented unique problems—namely, impacts to sensitive environmental resources. An avoidance option to the south was was never fully developed because it clearly would have impacted the entire community.

The Upgrade Alternative was eliminated because of the severe impacts it would have on the historic tavern, store, and hotel. Likewise, Alternative 1 was eliminated because of the severe impacts it would have on the cemetery and archeological mill site.

Although Alternative 3 would clip the northeast boundary of the historic district, it would not directly impact any contributing elements of the district or any elements that were individually historic, and any visual impacts associated with it would be minimized. Because Alternative 3 had no adverse effect, it was determined not to be a Section 4(f) use and was therefore the selected avoidance alternative.

Key points

  Next

SHA home page Return to top
 
Project examples