The purpose of a Section 4(f) draft evaluation is
to offer a description of a given project, as well as a description
of the property affected by the project, and the relevant impacts and
alternatives. The draft evaluation does not identify the selected alternative;
that discussion is reserved for the next step in the evaluation process,
the final evaluation.
When putting an evaluation together as part of the NEPA document, make
sure your Section 4(f) information is consistent with other references
and information throughout the rest of the EA or EIS. Also, be aware
that all Section 4(f) evaluations must undergo a legal
sufficiency review by the Federal
Highway Administration (FHWA). The review is intended to ensure
that Section 4(f) and NEPA requirements have been met, in case of a
legal challenge to Section 4(f) use. The data collected as part of the
evaluation may be used for legal purposes if necessary.
Below is a list of elements required for a draft evaluation. They should
be addressed in the following order:
Introduction
As a general guideline, consider beginning a Section 4(f) evaluation
by paraphrasing or directly quoting the following statement:
Back to List
Description of Proposed Action
For a separate Section 4(f) evaluation, describe the proposed project
alternatives, and explain the purpose and need for the project. For
an evaluation submitted with an EIS or EA/FONSI, briefly summarize and
reference the section of the National
Environmental Policy Act (NEPA) document that contains additional
detail about the project area and proposed alternatives.
Back to List
Description of Section 4(f) Resources
Describe each Section 4(f) resource that would be subject to use by
any alternative under consideration. Be sure to include the following
information:
Be sure to include maps or drawings such as this
one to illustrate the various project alternatives.
Be sure to quantify measurable impacts such as noise and affected functions
whenever possible. Impacts such as visual intrusions, which cannot be
quantified, should be described.
Back to List
Avoidance & Minimization Alternatives
A Section 4(f) evaluation must demonstrate that avoidance and minimization
alternatives to the project under consideration have been evaluated.
With respect to avoidance alternatives, specifically, the evaluation
must include a discussion that will ultimately support a determination
of whether or not an avoidance alternative is feasible and prudent in
the final evaluiation.
A determination that no feasible and prudent avoidance alternatives
exist is generally withheld until after the draft evaluation has been
circulated to the appropriate agencies and all issues have been appropriately
evaluated.
This discussion of feasibility and prudence must note whether any avoidance
alternatives present unique
problems or are prohibitively expensive, extraordinarily disruptive
to the community, somehow impractical or objectionable, or inadequate
to meet the project purpose and need.
Finally, the draft evaluation should address all possible measures
to minimize harm, including a separate discussion of each impact to
a Section 4(f) resource. For example, if multiple public parks are affected,
a separate discussion of each park should be provided, detailing how
impacts will be minimized. Be sure to include a least harm analysis
to show how efforts were made to minimize impacts to each alternative.
Back to List
Mitigation
All mitigation measures require appropriate documentation and coordination
between the state transportation agency and the official
with jurisdiction, including the State
Historic Preservation Officer (SHPO) when cultural resources are
involved.
Back to List
Coordination
Discuss the results of coordination with the following parties:
If any of these agencies raise issues during coordination, Section
4(f) requires follow-up coordination. While the statute does not stipulate
that these issues be resolved successfully, it does require reasonable
efforts and good-faith attention by decision makers.
Generally, the coordination should include a discussion of avoidance
alternatives, impacts to the property, and mitigation measures. In addition,
coordination with the public official with jurisdiction should include,
where necessary, a discussion of significance
and primary use of the property.